At Anybody Car Carriers, every build goes through multiple stages before it leaves the workshop, but one of the most important happens right at the end.
Fit-up is where the carrier transforms from a freshly painted structure into a fully operational piece of equipment ready for the road. It’s a stage that requires precision, experience and a sharp eye for detail. This month we’re taking you behind the scenes to highlight the crew responsible for that final step in the process: Andrew, Josh and Reece.
Where the Final Stage Begins
A build can spend up to a week in fit-up, depending on the configuration:
- Trailer: Around 2 days
- Cab frame, arms and top deck: Around 2½ days
Throughout the stages of fabrication, all the way through to paint and fit up the build goes through 3 QA’s to ensure everything meets the standard expected from an Australian Made Car Carrier.

Inside the Fit-Up Process
Cab Frame Assembly
Fit-up involves installing many of the operational components that allow the carrier to function safely and efficiently.
Some of the key jobs completed during this stage include fitting:
First, Punched flooring is fitted/welded into the build stage, wiring of lights and rubbers are installed. From there the power pack, isolation switch, hoses, reflectors and safety stickers are fitted.
Next, the hydraulic arms are mounted onto the cab frame, followed by installation of the top deck. Hydraulic control systems are also installed including: Buttons to operate the top deck on the cab frame. Then the cab frame is mounted onto the truck and the team then completes welding of the body mounts mounting a toolbox, water tank and mudguards.
At this stage, our in-house auto electrician steps in to complete the wiring, ensuring everything is properly connected and tested before the carrier moves on.
Trailer Assembly
Once a trailer has been suspended, the axels are mounted. The trailer also goes through a detailed process while it is suspended.
Fit-up involves installing many of the operational components, some of the key jobs completed during this stage include fitting:
While suspended, the crew assembles and mounts the axles and air bags under the trailer, including fitting the tyres and spare wheels for the trailer and truck.
During this stage the team also installs the airlines and wiring for the trailer lights.
- Marker lights and tail lights
- Punched flooring is fitted/welded in the build stage
- Spare tyres mounted on the underside of the trailer while it is still suspended, allowing the crew easy access during installation.
If the customer has opted for hydraulic ramp systems or manual ramps, the ramp racks are installed at this stage, along with the tail lights.
The very last thing is the team mounts the toolbox and fits on the mudflaps and the toolbox is stocked with the essentials:
- 16-wheel straps
- Landing leg for the trailer
- Wrench for removing tyres
- Optional – customers preference – ramp extensions.
Carriers fitted with manual ramps are also equipped with light boxes to assist operators during loading.

The Crew also Connects All Major Systems Including The Hydraulic Control Systems:
- Controls buttons for hydraulic ramps on the trailer (upon customers request)
- Raise and lower valves to manage air release and refill in the tanks
- Height adjustment valves to safely adjust trailer height during loading
Once the trailer is lowered back onto the ground, the trailer is then hitched to the trucks towbar using the Bartlett ball connection and fully coupled by cross over safety chains. All the plugs and connections are then plugged in under the truck:
- ABS connections
- Trailer plug lighting systems
- Male and female air lines
Testing and Final Checks
Once everything is assembled, the team performs full operational testing.
This includes testing the ramps and all control buttons for both the trailer and the top deck to ensure they are operating smoothly. Our in-house auto electrician completes final checks to confirm the ABS system and all lighting are working correctly. Once everything passes inspection, the carrier goes for a test drive to ensure all systems are operating exactly as they should. By the time a carrier leaves fit-up, it has gone from pieces of raw material to a fully operational machine ready to head straight to work. While customers see the finished carrier, the work done behind the scenes by the crew is what brings the build together.